I've been remiss in my blogging, but for a good cause.
Saturday went pretty well, all told. I got most of that 'punch list' done. Grizz and I bought hardware, I got the propane refilled and bought more landscape cloth, which I late returned.
Left to right, that is Grizz, Sean and yours truly. The three of us were scratching our heads looking at the site and discussing the options to level it off when Don the rock guy called. An hour later, we had this backing in through the side yard (borrowing the neighbor's lawn)
approximately 5 yards of gravel dumped roughly in the center of the shop site.
the LOML was shocked to see the pictures of the stone delivery. I guess she didn't expect an 8 wheeler like that in our back yard.
This was a multi-wood forum project, with Grizz from the WWA and Family Woodworking and my friend Sean from over on Woodnet helping out in a Huge way. Both guys brought tools and while we didn't use them all, the framing nailer was a great help, once we got better nails. 3.5's would jam occasionally but 3.25's worked just fine.
Sean took over the site prep and with my help we went from lumpy/wavy ground to 'screeded' stone, level in both directions. While we were doing that, Griz's circular saw reciprocating saw and sawhorses came in very handy, cutting those extra truss parts and joists.
That's Sean, aka the Rockmeister/framer/all around great guy. After smoothing out the stone, We ponka'd the rim joist into shape, and got creative when it came to squaring up the frame. I don't have a maul or sledge hammer, so I suggested that Sean use one of the concrete piers, three hits and it was square.
By the end of the day, this is where we wound up:
Somewhere in the middle of hanging the joists, I realized that I miscalculated the number of joists required. We wound up 1 joist short, which I didn't realize until Sunday after my lumber guy had delivered 10 2x8x12's which I had forgotten to order, but will need sometime next week.
That took a trip to Lowes and some adjustment to the materials list. they were Out of 2x8x12 PT, so I got a 2x10x12 with correct hanger instead. makes the entrance to the shop just a tad stronger than the rest of the floor, darn.
I briefly toyed with the idea of leaving the frame directly on the stone, but 'slept on it' and decided to put the piers back into action after all. Sunday went very smoothly, thanks to James and Adam, my two stepsons. With their help (thanks guys!), we got to this point:
Another new friend Mark from over on WOodnet came by as well, and despite him stapling his own hand with Lori's newfangled staple gun, we got a lot accomplished by dusk. Not 5 minutes after Mark stapled his hand, Lori did the same to her own! Ouch. both are recovering nicely, thanks for asking
Sean was back on Monday night, and we got more insulation installed and a few sheets of plywood installed as well when the insulation ran out.
Tuesday evening, I picked up two more rolls of insulation and then installed them. Rain was fast approaching, so I called it quits with the deck looking like this:
Tonight, I'm not out there at all, I'm very tired tonight, so I'm going to avoid power tools and get some shuteye. Thanks for looking!
Subscribe to: